We have completed the construction project the Strzelce Krajeńskie bypass

On February 15, 2025, the official opening of the Strzelce Krajeńskie bypass took place!

We have been working on this project since March 16, 2023, and the Colas team completed it ahead of schedule!

The aim of the investment was to move transit traffic out of the historic city centre, located on the route of national road No. 22, which increased safety and relieved local roads.

Strzelce Krajeńskie bypass in summary:

  • Length of the main route: 7.3 km,
  • Other roads with bicycle paths: about 6 km,
  • 4 intersections,
  • 4 bridges,
  • Approximately 310,000 m³ of earthworks,
  • Approximately 51,000 tons of aggregate,
  • Approximately 43,000 tons of MMA,
  • 8 retention reservoirs,
  • Several collisions, including 13 electro-power collisions,
  • Reconstruction of a high-pressure gas pipeline.

You can watch a video of the work here.